SANDAG Expenditures as of 01/20/2019
Caltrans Expenditures as of 12/31/2018


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,077,988$1,181,41856.85%45.71%
  I-15 Corridor
$1,403,215$1,297,05792.43%58.33%
  SR 52 Corridor
$503,775$500,13899.28%45.70%
  SR 76 Corridor
$368,820$356,84896.75%63.95%
  Orange Line - Blue Line Corridor
$573,431$572,27299.80%39.62%
  SR 94/SR 125 Corridor
$16,240$8,08649.79%38.36%
  SR 78/SPRINTER Corridor
$487,236$480,11698.54%38.13%
  I-5 North Corridor
$1,735,498$893,93551.51%44.90%
  Mid-City Corridor
$44,526$43,82598.42%89.09%
  I-805 Corridor
$684,981$616,14089.95%40.07%
  Border Access Corridor
$976,289$376,13938.53%59.52%