SANDAG Expenditures as of 06/30/2018
Caltrans Expenditures as of 06/30/2018


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,076,643$998,67448.09%43.80%
  I-15 Corridor
$1,408,306$1,292,39091.77%57.04%
  SR 52 Corridor
$514,088$500,15297.29%45.70%
  SR 76 Corridor
$368,820$355,07596.27%63.55%
  Orange Line - Blue Line Corridor
$567,784$571,898100.72%39.67%
  SR 94/SR 125 Corridor
$16,240$8,08649.79%39.73%
  SR 78/SPRINTER Corridor
$487,248$480,11698.54%29.17%
  I-5 North Corridor
$2,084,250$816,95939.20%42.17%
  Mid-City Corridor
$44,526$43,79698.36%89.09%
  I-805 Corridor
$688,239$591,70685.97%37.46%
  Border Access Corridor
$850,605$361,93342.55%55.70%