SANDAG Expenditures as of 05/27/2020
Caltrans Expenditures as of 04/30/2019


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,192,345$1,654,22775.45%50.29%
  I-15 Corridor
$1,405,507$1,308,02393.06%58.41%
  SR 52 Corridor
$503,775$500,13899.28%19.03%
  SR 76 Corridor
$368,820$358,82197.29%64.50%
  Orange Line - Blue Line Corridor
$573,431$572,87899.90%39.62%
  SR 94/SR 125 Corridor
$30,215$9,01729.84%38.36%
  SR 78/SPRINTER Corridor
$512,236$484,46194.58%-57.71%
  I-5 North Corridor
$1,642,856$1,131,07368.85%33.23%
  Mid-City Corridor
$44,526$44,07999.00%89.09%
  I-805 Corridor
$734,718$661,73090.07%35.26%
  Border Access Corridor
$994,873$449,08745.14%58.74%