SANDAG Expenditures as of 06/30/2020
Caltrans Expenditures as of 06/30/2020


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,160,562$1,733,66780.24%54.14%
  I-15 Corridor
$1,093,319$1,308,137119.65%51.21%
  SR 52 Corridor
$460,509$500,138108.61%19.03%
  SR 76 Corridor
$206,591$359,040173.79%65.32%
  Orange Line - Blue Line Corridor
$240,155$572,889238.55%31.37%
  SR 94/SR 125 Corridor
$30,215$9,82432.51%22.45%
  SR 78/SPRINTER Corridor
$105,937$484,634457.47%-27.21%
  I-5 North Corridor
$1,728,532$1,161,02167.17%25.36%
  Mid-City Corridor
$2,109$44,0792090.03%89.09%
  I-805 Corridor
$662,604$669,472101.04%35.58%
  Border Access Corridor
$953,141$462,43748.52%39.81%