SANDAG Expenditures as of 10/21/2020
Caltrans Expenditures as of 09/30/2020


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,192,023$1,809,34382.54%55.86%
  I-15 Corridor
$1,408,108$1,308,19192.90%51.23%
  SR 52 Corridor
$503,775$500,13899.28%19.03%
  SR 76 Corridor
$368,820$359,31697.42%65.32%
  Orange Line - Blue Line Corridor
$650,531$572,98688.08%31.38%
  SR 94/SR 125 Corridor
$30,240$11,96339.56%22.45%
  SR 78/SPRINTER Corridor
$588,365$485,59682.53%-26.43%
  I-5 North Corridor
$1,862,592$1,199,18664.38%27.92%
  Mid-City Corridor
$44,526$44,08099.00%89.09%
  I-805 Corridor
$834,454$685,02782.09%27.49%
  Border Access Corridor
$1,075,734$479,90644.61%40.62%