Note: All monetary values are in $000s
I-5 South Corridor | | $2,192,423 | $1,920,552 | 87.60% | 51.85% |  |
I-15 Corridor | | $1,408,108 | $1,308,285 | 92.91% | 45.41% |  |
SR 52 Corridor | | $503,775 | $500,138 | 99.28% | 19.03% |  |
SR 76 Corridor | | $368,820 | $359,692 | 97.52% | 66.64% |  |
Orange Line - Blue Line Corridor | | $650,531 | $573,083 | 88.09% | 26.28% |  |
SR 94/SR 125 Corridor | | $30,240 | $13,661 | 45.18% | 16.27% |  |
SR 78/SPRINTER Corridor | | $588,365 | $487,064 | 82.78% | -25.98% |  |
I-5 North Corridor | | $1,861,592 | $1,262,358 | 67.81% | 28.18% |  |
Mid-City Corridor | | $44,526 | $44,082 | 99.00% | 80.00% |  |
I-805 Corridor | | $834,454 | $693,981 | 83.17% | 26.14% |  |
Border Access Corridor | | $1,112,214 | $514,812 | 46.29% | 37.77% |  |
| Administration | $8,035 | $6,307 | 78.49% | N/A |  |
| Environmental | $1,536 | $8,361 | 544.31% | 22.22% |  |
| Design | $86,040 | $58,181 | 67.62% | 78.00% |  |
| ROW Support | $9,947 | $4,837 | 48.63% | 45.89% |  |
| ROW Capital | $141,118 | $88,411 | 62.65% | N/A |  |
| Const. Support | $115,181 | $50,465 | 43.81% | 54.42% |  |
| Const. Capital | $737,895 | $296,189 | 40.14% | N/A |  |
| Legal Services | $6,206 | $1,373 | 22.12% | N/A |  |
| Communications | $1,492 | $689 | 46.16% | N/A |  |
| Project Contingency | $4,764 | $0 | 0.00% | N/A |  |
|