SANDAG Expenditures as of 01/20/2019
Caltrans Expenditures as of 12/31/2018


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,077,988$1,181,41856.85%45.40%
  I-15 Corridor
$1,403,215$1,297,05792.43%58.33%
  SR 52 Corridor
$503,775$500,13899.28%45.70%
  SR 76 Corridor
$368,820$356,84896.75%63.95%
  Orange Line - Blue Line Corridor
$573,431$572,27299.80%39.67%
  SR 94/SR 125 Corridor
$16,240$8,08649.79%38.36%
  SR 78/SPRINTER Corridor
$487,236$480,11698.54%38.13%
 Administration$86$10,63612376.10%N/A
 Environmental$32,945$15,32446.51%37.00%
 Design$30,617$30,617100.00%33.33%
 ROW Support$2,886$2,88699.99%66.00%
 ROW Capital$54,830$54,830100.00%N/A
 Const. Support$36,853$36,853100.00%33.33%
 Const. Capital$328,969$328,969100.00%N/A
 Legal Services$0$00.00%N/A
 Communications$50$00.00%N/A
 Project Contingency$0$00.00%N/A
  I-5 North Corridor
$1,735,498$893,93551.51%44.14%
  Mid-City Corridor
$44,526$43,82598.42%89.09%
  I-805 Corridor
$684,981$616,14089.95%39.75%
  Border Access Corridor
$976,289$376,13938.53%58.23%