SANDAG Expenditures as of 10/16/2017
Caltrans Expenditures as of 09/30/2017


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,050,964$726,86335.44%46.70%
  I-15 Corridor
$1,411,398$1,281,76090.81%54.49%
  SR 52 Corridor
$514,088$500,15297.29%45.70%
  SR 76 Corridor
$363,908$344,91694.78%63.09%
  Orange Line - Blue Line Corridor
$567,695$569,022100.23%39.55%
  SR 94/SR 125 Corridor
$10,654$8,08675.90%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,105100.00%29.17%
  I-5 North Corridor
$1,306,556$668,87951.19%39.93%
  Mid-City Corridor
$44,478$42,08894.63%77.45%
  I-805 Corridor
$684,924$542,45179.20%36.21%
  Border Access Corridor
$484,724$342,75270.71%55.78%