SANDAG Expenditures as of 09/18/2018
Caltrans Expenditures as of 08/31/2018


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,077,988$1,046,19250.35%44.65%
  I-15 Corridor
$1,403,215$1,296,27392.38%57.55%
  SR 52 Corridor
$514,088$500,14297.29%45.70%
  SR 76 Corridor
$368,820$356,03496.53%63.73%
  Orange Line - Blue Line Corridor
$567,684$572,077100.77%39.67%
  SR 94/SR 125 Corridor (Completed)
$16,240$8,08649.79%38.27%
  SR 78/SPRINTER Corridor
$487,248$480,11698.54%40.92%
  I-5 North Corridor
$2,106,193$841,89339.97%43.00%
  Mid-City Corridor
$44,526$43,80998.39%89.09%
  I-805 Corridor
$692,481$600,05986.65%38.29%
  Border Access Corridor
$976,888$363,70937.23%56.73%