SANDAG Expenditures as of 08/17/2019
Caltrans Expenditures as of 07/31/2019


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,141,588$1,402,17865.47%48.56%
  I-15 Corridor
$1,403,215$1,308,07093.22%58.41%
  SR 52 Corridor
$503,775$500,13899.28%45.70%
  SR 76 Corridor
$368,820$357,88297.03%64.50%
  Orange Line - Blue Line Corridor
$573,431$572,78899.89%39.62%
  SR 94/SR 125 Corridor
$16,240$8,16650.28%38.36%
  SR 78/SPRINTER Corridor
$487,236$480,51598.62%38.13%
  I-5 North Corridor
$3,266,437$1,016,41731.12%46.72%
  Mid-City Corridor
$44,526$43,84898.48%89.09%
  I-805 Corridor
$686,063$637,99092.99%40.61%
  Border Access Corridor
$976,289$390,34139.98%59.71%