SANDAG Expenditures as of 04/28/2021
Caltrans Expenditures as of 03/31/2021


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,192,423$1,925,13687.81%51.85%
  I-15 Corridor
$1,408,108$1,308,30092.91%45.41%
  SR 52 Corridor
$503,775$500,13899.28%19.03%
  SR 76 Corridor
$368,820$359,72297.53%66.64%
  Orange Line - Blue Line Corridor
$650,531$573,09688.10%23.77%
  SR 94/SR 125 Corridor
$30,240$13,66145.18%16.27%
  SR 78/SPRINTER Corridor
$588,365$487,10382.79%-25.98%
  I-5 North Corridor
$1,861,592$1,265,66567.99%28.18%
  Mid-City Corridor
$44,526$44,08299.00%80.00%
  I-805 Corridor
$834,454$694,41883.22%26.14%
  Border Access Corridor
$1,112,214$515,36446.34%37.77%