SANDAG Expenditures as of 03/25/2021
Caltrans Expenditures as of 02/28/2021


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,192,423$1,920,55287.60%51.85%
  I-15 Corridor
$1,408,108$1,308,28592.91%45.41%
  SR 52 Corridor
$503,775$500,13899.28%19.03%
  SR 76 Corridor
$368,820$359,69297.52%66.64%
  Orange Line - Blue Line Corridor
$650,531$573,08388.09%26.28%
  SR 94/SR 125 Corridor
$30,240$13,66145.18%16.27%
  SR 78/SPRINTER Corridor
$588,365$487,06482.78%-25.98%
  I-5 North Corridor
$1,861,592$1,262,35867.81%28.18%
  Mid-City Corridor
$44,526$44,08299.00%80.00%
  I-805 Corridor
$834,454$693,98183.17%26.14%
 Administration$15,588$13,13284.24%N/A
 Environmental$118,524$73,21861.78%38.76%
 Design$108,760$89,53582.32%39.72%
 ROW Support$10,353$7,93476.63%34.71%
 ROW Capital$19,590$9,81450.10%N/A
 Const. Support$113,712$100,43988.33%27.24%
 Const. Capital$441,815$397,73190.02%N/A
 Legal Services$262$18470.33%N/A
 Communications$3,019$1,99366.03%N/A
 Project Contingency$2,832$00.00%N/A
  Border Access Corridor
$1,112,214$514,81246.29%37.77%