SANDAG Expenditures as of 11/20/2020
Caltrans Expenditures as of 10/31/2020


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,192,023$1,840,81783.98%55.86%
  I-15 Corridor
$1,408,108$1,308,21692.91%51.23%
  SR 52 Corridor
$503,775$500,13899.28%19.03%
  SR 76 Corridor
$368,820$359,43597.46%65.32%
  Orange Line - Blue Line Corridor
$650,531$573,01388.08%31.38%
  SR 94/SR 125 Corridor
$30,240$12,27340.59%22.45%
  SR 78/SPRINTER Corridor
$588,365$485,90282.59%-26.43%
  I-5 North Corridor
$1,861,592$1,212,48265.13%27.92%
  Mid-City Corridor
$44,526$44,08199.00%89.09%
  I-805 Corridor
$834,454$686,92482.32%27.49%
  Border Access Corridor
$1,075,734$488,07145.37%40.62%