SANDAG Expenditures as of 04/17/2018
Caltrans Expenditures as of 03/31/2018


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,052,243$912,81244.48%42.34%
  I-15 Corridor
$1,411,398$1,290,62591.44%56.21%
  SR 52 Corridor
$514,088$500,15297.29%45.70%
  SR 76 Corridor
$363,908$350,78596.39%63.32%
  Orange Line - Blue Line Corridor
$567,695$571,758100.72%39.67%
  SR 94/SR 125 Corridor
$10,654$8,08675.90%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,116100.00%29.17%
  I-5 North Corridor
$1,690,560$777,41145.99%40.90%
  Mid-City Corridor
$44,478$43,16797.05%86.36%
  I-805 Corridor
$684,924$560,32981.81%36.77%
  Border Access Corridor
$538,276$356,05266.15%55.01%