SANDAG Expenditures as of 01/05/2018
Caltrans Expenditures as of 11/30/2017


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,050,964$816,62639.82%46.28%
  I-15 Corridor
$1,411,398$1,286,22991.13%55.23%
  SR 52 Corridor
$514,088$500,15297.29%45.70%
  SR 76 Corridor
$363,908$347,22395.42%63.32%
  Orange Line - Blue Line Corridor
$567,695$571,598100.69%39.66%
  SR 94/SR 125 Corridor
$10,654$8,08675.90%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,114100.00%29.17%
  I-5 North Corridor
$1,586,457$714,36845.03%40.34%
  Mid-City Corridor
$44,478$42,95296.57%77.45%
  I-805 Corridor
$684,924$550,37680.36%36.14%
  Border Access Corridor
$484,724$345,08471.19%55.84%