SANDAG Expenditures as of 09/20/2017
Caltrans Expenditures as of 08/31/2017


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,050,964$685,06233.40%44.41%
  I-15 Corridor
$1,411,398$1,279,69790.67%53.80%
  SR 52 Corridor
$514,088$500,15297.29%45.70%
  SR 76 Corridor
$363,908$342,94594.24%62.50%
  Orange Line - Blue Line Corridor
$567,695$568,926100.22%39.13%
  SR 94/SR 125 Corridor
$10,654$8,08675.90%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,09799.99%29.17%
  I-5 North Corridor
$1,306,556$644,91949.36%39.75%
  Mid-City Corridor
$44,478$41,91594.24%77.45%
  I-805 Corridor
$664,924$539,67581.16%36.14%
  Border Access Corridor
$484,724$321,97866.42%52.19%