SANDAG Expenditures as of 04/22/2022
Caltrans Expenditures as of 03/31/2022
Budget Detail as of 6/30/2021


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,227,298$2,150,13696.54%53.21%
  I-15 Corridor
$1,404,207$1,308,80893.21%45.75%
  SR 52 Corridor
$515,775$500,13896.97%13.93%
  SR 76 Corridor
$368,820$360,85697.84%66.64%
  Orange Line - Blue Line Corridor
$578,791$573,40799.07%24.29%
  SR 94/SR 125 Corridor
$30,240$18,61861.57%20.82%
  SR 78/SPRINTER Corridor
$588,365$493,10083.81%-25.88%
  I-5 North Corridor
$2,397,334$1,424,29959.41%28.79%
  Mid-City Corridor
$44,526$44,08399.00%81.36%
  I-805 Corridor
$836,254$702,49084.00%27.03%
  Border Access Corridor
$1,169,134$599,94551.32%41.10%