SANDAG Expenditures as of 12/23/2021
Caltrans Expenditures as of 11/30/2021
Budget Detail as of 6/30/2021


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,227,298$2,103,39094.44%52.33%
  I-15 Corridor
$1,404,207$1,308,73093.20%45.50%
  SR 52 Corridor
$515,775$500,13896.97%13.93%
  SR 76 Corridor
$368,820$360,57197.76%66.64%
  Orange Line - Blue Line Corridor
$578,791$573,19299.03%24.29%
 Administration$19,552$18,89096.62%N/A
 Environmental$471$471100.00%9.09%
 Design$30,948$26,59485.93%36.36%
 ROW Support$33$33100.28%9.09%
 ROW Capital$841$84099.87%N/A
 Const. Support$35,232$35,22099.97%39.64%
 Const. Capital$491,035$490,73099.94%N/A
 Legal Services$64$6399.13%N/A
 Communications$400$35087.47%N/A
 Project Contingency$215$00.00%N/A
  SR 94/SR 125 Corridor
$30,240$17,14256.69%18.09%
  SR 78/SPRINTER Corridor
$588,365$491,38083.52%-25.88%
  I-5 North Corridor
$2,397,334$1,372,96157.27%26.99%
  Mid-City Corridor
$44,526$44,08299.00%80.00%
  I-805 Corridor
$836,254$700,76683.80%26.74%
  Border Access Corridor
$1,169,134$568,69748.64%39.17%