SANDAG Expenditures as of 01/20/2020
Caltrans Expenditures as of 12/31/2019


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,142,345$1,557,48172.70%48.65%
  I-15 Corridor
$1,405,507$1,308,20693.08%58.41%
  SR 52 Corridor
$503,775$500,13899.28%45.70%
  SR 76 Corridor
$368,820$358,28797.14%64.50%
 Administration$3,128$2,98795.48%N/A
 Environmental$25,788$25,787100.00%100.00%
 Design$35,578$35,577100.00%97.50%
 ROW Support$15,160$13,19087.00%92.50%
 ROW Capital$47,267$48,298102.18%N/A
 Const. Support$44,514$43,15196.94%94.50%
 Const. Capital$196,875$189,04296.02%N/A
 Legal Services$0$00.00%N/A
 Communications$257$25599.30%N/A
 Project Contingency$253$00.00%N/A
  Orange Line - Blue Line Corridor
$573,431$572,83299.90%39.62%
  SR 94/SR 125 Corridor
$30,215$8,37027.70%38.36%
  SR 78/SPRINTER Corridor
$512,236$481,21393.94%38.13%
  I-5 North Corridor
$1,643,549$1,090,12366.33%46.72%
  Mid-City Corridor
$44,526$43,85398.49%89.09%
  I-805 Corridor
$734,718$653,02888.88%40.97%
  Border Access Corridor
$994,873$435,72743.80%58.28%